The roads Authority has spent about K600 million compensating people affected by the 95-kilometre Lilongwe Old Airport-Kasiya- Santhe Road project, Chief Executive Officer, Emmanuel Matapa, said over the weekend
Matapa said the project has been delayed because of the issue of compensating all the people living along the stretch that took time
“The challenge of compensating people is what has delayed the whole project, but now that we have completed compensating the people, the contractor is now free to start work and finish the remaining 37 km ‚” Matapa said.Advertisement
Minister of Transport and Public works Jappie Mhango on Friday travelled along the road to check progress made so far.
During the visit, Matapa said although they faced challenges in the initial stages of the project, they are happy that the project is now progressing well.
Mhango said the new road will help people of the area enormously as the area is rich in agriculture and is one of the areas that contributes significantly to the economic growth.